{ "@context": "https://schema.org", "@type": "HowTo", "name": "Installation Procedure for Blue Cold Freon Evaporator - Wiring during installation", "description": "Comprehensive engineering field manual outlining the physical placement, refrigeration piping connections, and wiring sequence for Freon Evaporator - Wiring during installation.", "totalTime": "PT4H", "estimatedCost": { "@type": "MonetaryAmount", "currency": "USD", "value": "0" }, "step": [ { "@type": "HowToStep", "url": "https://www.bluecoldref.com/installation-procedure/wiring-during-installation#step1", "name": "Unpacking and Structural Mounting", "text": "Inspect the unit chassis for shipping damage. Verify mounting point dimensions and lift the unit into place using structural hangers or support channels capable of handling the operating weight." }, { "@type": "HowToStep", "url": "https://www.bluecoldref.com/installation-procedure/wiring-during-installation#step2", "name": "Refrigeration Piping & Brazing", "text": "Route copper suction and liquid lines ensuring a continuous slope toward the compressor. Flow dry nitrogen through the lines while brazing joints to prevent internal oxide scaling." }, { "@type": "HowToStep", "url": "https://www.bluecoldref.com/installation-procedure/wiring-during-installation#step3", "name": "Pressure Leak Testing and Evacuation", "text": "Pressurize the system with dry nitrogen to the target design pressure and hold for 24 hours. Once leak-free, evacuate the system using a dedicated vacuum pump down to a deep vacuum below 500 microns." }, { "@type": "HowToStep", "url": "https://www.bluecoldref.com/installation-procedure/wiring-during-installation#step4", "name": "Electrical Connection and Pre-Commissioning", "text": "Connect the main three-phase power lines and link control sensors to the digital thermostat board. Verify fan rotation direction before introducing refrigerant." } ] }

Installation Procedure

Back

Freon Evaporator - Wiring during installation

The field wiring should enter the areas as provided on the unit. The wiring diagram for each unit is located on the inside of the electrical panel door. All field wiring should be done in a professional manner and in accordance with all governing codes. Before operating unit, double check all wiring connections, including the factory terminals. Factory connections can vibrate loose during shipment.

  1. The serial data tag on the unit is marked with the electrical characteristic for wiring the unit.
  2. Consult the wiring diagram in the unit cooler and in the condensing unit for proper connections.
  3. Wire type should be of copper conductor only and of the proper size to handle the connected load.
  4. The unit must be grounded.
  5. For multiple evaporator systems, the defrost termination controls should be wired in series. Follow the wiring diagrams for multiple evaporator systems carefully. This will assure complete defrost of all evaporators in the system.
  6. Multiple evaporator systems should operate of one thermostat.
  7. If a remote defrost timer is to be used, the timer should be located outside the refrigerated space.